Phase 2 Community meeting v5 040710 FINAL - English

A national leader in heavy civil design-build transportation projects. ▫. STEVE P. RADOS, INC. (Builder). •. 87 years of experience building transportation projects ...
3MB Größe 6 Downloads 33 vistas
Thursday, July 29, 2010

6:30 p.m. - 8:00 p.m.

Expo Light Rail Line

Project Status Update Open House / Downtown & Mid-Corridor Thursday, July 29, 2010Phase 6:302p.m. - 8:00Kick-Off .m. Design Meetings Help us kick-off the design process for Expo Phase 2!

The Exposition Construction Authority invites you to a community meeting to kick-off the design process for Phase 2 of the Expo Line project. Stakeholders will have the opportunity to meet the design/build contractor Skanska/Rados, a Joint Venture, and learn about the design process and timeline. The format will include a short presentation followed by breakout sessions to facilitate dialogue and community input on station elements, neighborhood integration and mitigation measures. The information presented at these meetings will be identical, so interested individuals, organizations and public agencies are welcome to attend on either of the following days:

Planned Agenda for Community Meetings 6:30 - 7:00 pm: Formal Presentation 7:00 - 8:00 pm: Breakout Sessions

Monday, May 9, 2011

Wednesday, May 11, 2011

Santa Monica Civic Auditorium East Wing Meeting Room 1855 Main Street Santa Monica, CA 90401

Vista Del Mar Child and Family Services Gymnasium 3200 Motor Avenue Los Angeles, CA 90034

Special Event free parking available off Main Street

Parking available on campus

ADA Language Accommodation: If you require an interpreter, including sign language services, or other accommodations at these community meetings, please contact Expo at least five business days prior to the meeting date at 213-922-3976. For more information about the Expo Line project, visit BuildExpo.org or call 213.922.EXPO (3976). Find us on

www.Facebook.com/ExpoLine and follow us on

@ExpoLine

Thursday, July 29, 2010

6:30 p.m. - 8:00 p.m.

Línea de Tren Ligero Expo

Project Status Update Open House / Downtown & Mid-Corridor Thursday, July 29, 2010 de 6:30 p.m. - para 8:00 .m. Reuniones Diseño la Segunda Fase

Ayúdenos a iniciar el proceso de diseño para la Segunda Fase! Las Autoridades de Construcción Exposition le invitan a una reunión comunitaria para dar inicio al proceso de diseño de la Segunda Fase del proyecto Línea Expo. La personas interesadas tendrán la oportunidad de conocer al contratista de diseño y construcción Skanska/Rados, una empresa conjunta, y aprender sobre el proceso de diseño y la secuencia de eventos. El formato incluirá una presentación breve seguida por sesiones de discurso para facilitar el diálogo con la comunidad sobre los elementos de las estaciones, la integración de vecindad y las medidas de mitigación. El contenido que se presente en estas reuniones será el mismo. Por lo tanto, individuos, organizaciones y agencias públicas con interés en el proyecto están invitados a asistir en cualquier día:

Expo LightMiércoles, Rail11Line de mayo, 2011

Orden del día para Reuniones Comunitarias

Lunes, 9 de mayo, 2011

6:30 - 7:00 pm: Presentación Formal

Santa Monica Civic Auditorium East Wing Meeting Room 1855 Main Street Santa Monica, CA 90401

Vista Del Mar Child and Family Services Gymnasium 3200 Motor Avenue Los Angeles, CA 90034

Estacionamiento gratuito con entrada sobre Main Street

Estacionamiento disponible dentro del campus

7:00 - 8:00 pm: Sesiones de Discurso

Ajustes de ADA (Ley de Americanos con Discapacidades) y relacionados con el idioma: Si necesita a un intérprete, incluyendo servicios de lenguaje de señas, u otros ajustes en estas reuniones comunitarias, por favor comuníquese con Expo cinco días antes de la reunión llamando al 213-922-3976. Para más información sobre el proyecto Línea Expo, visite BuildExpo.org o llame al 213.922.EXPO (3976).

Encuéntrenos en

www.Facebook.com/ExpoLine y síganos en

@ExpoLine

Expo Light Rail Line

Expo Line Community Meeting Phase 2 Design Kick-Off May 2011

Expo Light Rail Line Phase 2 Design Kick-Off Meetings  Meeting Purpose and Format  Project Status Update

 Introduction of Design-Build Team  Overview of Design Process and Timeline

 Next Steps  Open House Session

Meeting Agenda

Expo Light Rail Line

Meeting Purpose and Format

Meeting Purpose and Format The purpose of tonight’s meeting is to: 

Introduce the design-build contractor



Share information about the design process and timeline



Receive input from the community on design elements

The format will include a short presentation followed by an interactive Open House session to facilitate dialogue and community input. Please be sure to visit all the stations and: 

Collect information



Ask questions



Share your ideas

Expo Light Rail Line

Expo Line Project Description

Expo Line from Downtown Los Angeles to Santa Monica:  15.2 mile corridor  19 Stations, 2 Shared with Blue Line  64,000 Daily Riders by 2030  Estimated Travel Time: 46 minutes  Estimated Cost: $2.4 billion

 Constructed in Two Phases: • Phase 1 - Downtown to Culver City • Phase 2 - Culver City to Santa Monica

Expo Light Rail Line

Project Alignment Map

Expo Light Rail Line Phase 1 from Downtown Los Angeles to Culver City:  Construction is 90% complete  Anticipate opening to Jefferson/La Cienega station later this year

 Opening to Culver City station in early 2012  Train testing is underway along the alignment and will continue for several months

Phase 1 Update

Expo Light Rail Line

Phase 2 Update

Phase 2 from Culver City to Santa Monica:  February 2010: Expo Board certified FEIR  May – November 2010: Preliminary Engineering  March 2011: Design-Build contract awarded to Skanska/Rados, Joint Venture  Begin final design process with community input

Expo Light Rail Line

Design Overview

Project Elements to Undergo Design Process 

Light Rail System • Design-Build Contract • Contractor: Skanska-Rados Joint Venture



Maintenance Facility • Design Contract • Designer: Maintenance Design Group • Once final design is complete, will issue Invitation for Bid for a construction contract



Bikeway

• • • •

Pending board authorization to design and build the project Preliminary Engineering (PE) Contract Designer: TBD Once PE is complete, will issue Request for Proposals for a design-build contract

Expo Light Rail Line

Design Overview

Design Input 

Community Input • Community meetings as the design progresses • Regular stakeholder briefings



Urban Design Committee • 14 member committee appointed by the Expo Board • Members represent communities and stakeholders along the alignment • Provided input into design elements during Phase 1 • Provide input into station elements, landscaping and public art for Phase 2



Bikeway Advisory Committee • Pending board authorization, plan to convene advisory committee to help refine bikeway design



Third Parties • Work closely with cities of Los Angeles and Santa Monica staff and other public agencies during the design process

Expo Light Rail Line

Design Overview

Expo Line Urban Design Elements 

Multi-modal transit parkway that includes bikeway facilities and pedestrian linkages



Station architecture that provides continuity across the alignment (Phase 1 and Phase 2)



Vertical elements that complement the station canopy design



Variations in station landscaping and public art to distinguish individual neighborhoods



Environmentally cleared to be consistent with Expo Phase 1

Expo Light Rail Line

Design-Build Team

Introduction of Design-Build Team 



SKANSKA CIVIL USA (Builder) •

Ranked 6th largest contractor in the nation and in the world (per Engineering News Record)



80 years of local experience



A national leader in heavy civil design-build transportation projects

STEVE P. RADOS, INC. (Builder) •



87 years of experience building transportation projects in the City and County of Los Angeles 

Metro Gold Line – Pasadena



Metro Gold Line – Eastside Extension

PARSONS BRINCKERHOFF (Designer) • Provides multidisciplinary engineering services for all types of transportation projects

Expo Light Rail Line Overview of Final Design Process and Timeline 

Moving from Preliminary Engineering stage to: •

65% Design Development



85% Design Development



Final Design



Final design process is anticipated to take approximately 18 months



Construction work starts prior to completion of final design



Design-Build process speeds up project completion

Design Process

Design Process

Expo Light Rail Line Overview of Final Design Process and Timeline

Design Kick-Off

65% Design Development

85% Design Development

Regular updates to community and stakeholder groups on design progress and neighborhood specific issues

Final Design

Expo Light Rail Line

Next Steps

Next Steps in the Design Process 

Begin design development process



Work with the community and incorporate ideas where feasible



Work with Urban Design Committee on design elements



Work with Bikeway Advisory Committee to refine bikeway design



Provide regular updates to stakeholder groups throughout the process



Host community meetings at key milestones to provide updates on design progress

Open House Session

Expo Light Rail Line

The room is divided into stations where you can meet with project staff that can address your questions/concerns and receive your feedback regarding: STATION Station Elements

PURPOSE View design renderings and conceptual site plans of the stations Speak with project staff about station elements Share your ideas on neighborhood integration

Mitigation Measures

View alignment maps that identify locations for noise mitigation Speak with technical experts about mitigations included in the project Find out more about construction mitigation measures

General Information, Local Jobs Program and Contracting Opportunities

Receive general information about the project Find out more about the Local Jobs Program and SBE opportunities

Fill out a comment sheet outlining any comments and/or concerns