20170525 Schedule Summary to Evan.xlsx

25 may. 2017 - 630. Days. Contract final completion date: 25-Sep-17. 21-Month construction duration per construction contract. 11-Month contractor delay. Jan.
112KB Größe 5 Downloads 31 vistas
Summary of Construction Schedule  Stewart Creek WWTP Expansion ‐ Phase 1

Notice to Proceed Date: 4‐Jan‐16 Contract days to substantial completion: 583 Days Contract substantial completion date: 9‐Aug‐17 Contract days to final completion: 630 Days Contract final completion date: 25‐Sep‐17

S = F = A = B = C =

Substantial Completion Final Completion Train A substantial completion Train B substantial completion Train C substantial completion

C

A, B

S

Oct‐18

Sep‐18

Aug‐18

Jul‐18

Jun‐18

May‐18

Apr‐18

Mar‐18

Feb‐18

Dec‐17

Nov‐17

Oct‐17

Sep‐17

Aug‐17

Jul‐17

Jun‐17

May‐17

Apr‐17

Mar‐17

Feb‐17

Jan‐17

Dec‐16

Nov‐16

Oct‐16

Sep‐16

Aug‐16

Jul‐16

Jun‐16

May‐16

Apr‐16

Mar‐16

Feb‐16

Jan‐16 Baseline (contract) schedule

Jan‐18

11‐Month contractor delay

21‐Month construction duration per construction contract

F

32‐Month construction duration based on April 2017 schedule update April 2017 Schedule update

C

A, B

S

F

13‐Month delay completing Train C 11‐Month Delay completing A and B 10‐Month delay overall substantial 11‐Month delay in overall final

Page 1 of 1

Printed: 5/26/20172:31 PM